Soil contamination delays housing project in Boden
Soil contamination at the site where Surewood plans to build new semi-detached and terraced houses in Prästholmen is more extensive than previous investigations indicated. Boden Municipality therefore needs to carry out further investigations and remediation work. The housing project will be delayed, but the plans for the new homes remain unchanged.
The contamination affects the Ägir property in Prästholmen, near Prästholm school, where Surewood plans to build 41 new rental homes.
It was already known that parts of the site were contaminated. New investigations have now shown that the contamination extends over a larger area and is more complex to address than previously understood. The contamination mainly consists of oil and metals found in the soil and groundwater.
“These are environmental legacies from past activities that we now need to address as the site is prepared for a new use. We know more about the contamination today and need to carry out the necessary work to ensure that the land is safe and suitable for housing,” says Ellinor Isaksson Larsson, Head of Planning and Land Development at Boden Municipality.
Ellinor Isaksson Larsson, Head of Planning and Land Development at Boden Municipality.
Legacy of previous activities
The contamination is linked to how the land was used in the past. Until the late 1960s, parts of the site were used as a landfill. The site was subsequently used for various municipal facilities, including a vehicle workshop, car wash and lubrication facility.
The municipality is now taking additional samples to determine where the contamination is located and the extent of the affected area. Once this is clear, it will be possible to determine what remediation work is required.
The homes will still be built
The additional work affects the timeline for Surewood’s housing project. Planning permission, project planning and other preparations have already been completed. However, the necessary groundwork and foundation work cannot begin until the land has been remediated.
Residents were previously expected to move in from April 2027. That timeline can no longer be maintained. A new date can only be set once the required remediation measures and the time needed to complete them are known.
The plans for the 41 homes remain unchanged.
“We would of course have preferred to keep to the original timeline, but the important thing is to ensure that the land is ready for construction. The project is moving forward and much of the preparatory work has already been completed. We are ready to proceed as soon as the site is ready,” says Fredrik Anheim, CEO of Surewood.
byline
Text by: André Samuelsson
Photo by: Patrik Öhman, Mats Engfors
Published: